(1.) THIS Miscellaneous Appeal is directed as against the order dated 11.10.2006 in MA -295/2005 in OA -450/2000 passed by the DRT -I at Chennai.
(2.) THE appellants and the respondent bank have settled their claim before the Lok Adalat, and an award was passed by the Lok Adalat on 10.9.2004 permitting the appellants to pay the amounts on or before 10.12.2004 with certain conditions, and the appellants were not able to pay the amounts within the stipulated date, and had approached the bank to extend the time fixed by the Lok Adalat, and the bank had extended the time till 20.1.2005. Even, within the said time, the appellants could not pay the amount. But, however, they paid a sum of Rs. 3 lakh on 8.2.2005. As the entire amount was not paid, DRC was issued on 21.10.2005, and thereafter the appellants have filed three applications, (1) for extension of time to comply with the award of the Lok Adalat, (2) to condone the delay of 320 days in filing the petition for extension of time, and (3) for stay of recovery proceedings. The application to condone the delay in MA -295/2005 came to be dismissed by the DRT by its order dated 11.10.2006. Aggrieved by the same, the appellants have preferred his appeal.
(3.) THE point for consideration is whether the Courts/Tribunal are empowered to enlarge the time granted by the Lok Adalat for the payment of the award amount.