LAWS(CE)-1994-9-5

COLLECTOR OF CENTRAL EXCISE Vs. RALIWEX INDIA

Decided On September 17, 1994

JUDGEMENT

(1.) COLLECTOR of Central Excise has filed this appeal against the order of Addl. COLLECTOR of Central Excise. The Additional COLLECTOR in his order had held:

(2.) Briefly stated the facts of the case are that M/s Raliwex India the respondents in this case are engaged in the manufacture of Electric Wires and Cables. The appellant manufactured 16,961.750 Kgs of bare Copper Wire upto 13 SWG from duty paid Copper Rod and captively used the said intermediate goods in their factory after subjecting them to further process of drawing or otherwise in the manufacture of their said finished goods namely electric wires and cables during the period from 20th February, 1982 to 8th July, 1983 without payment of duty amounting to Rs. 77,294.70 in terms of Notfn. No. 20/82 dated 20.2.1982. A show cause notice was issued to the appellant on 29.2.1984 asking them to show cause to the Additional Collector as to why Central Excise duty as indicated above leviable on 16,961.750 kgs of bare Copper Wire manufactured and consumed during the material period should not be demanded and recovered from them under Section 11A of the said Act, and why a penalty should not be imposed on them. They were also asked to explain why time limit of 5 years should not be invoked for recovery of duty for their wilful contravention of the said rules.

(3.) SH. B. Saha, the Id. Advocate for the respondent submitted that under the Central Excise law duty is leviable on the goods. The goods should be so specified in the Central Excise Tariff and should be known to the market as goods. He submitted that the respondent was engaged in the manufacturing of Electric Wires and Cables. The drawing of Wires and Cables from Rods/Bars necessarily requires the passing of the Wire through a number of dyes and thereby correspondingly diminishing the cross-section of the wire; that they were utilising wire Rods of 8 mm and were finally drawing Wire finer than 14 SWG and that there were 9 dies used in the entire process of wire drawing. Thus at these 9 stages, Wire of different cross-section was emerging. However, their finished product was wire finer than 14 SWG which was exempted from payment of duty. The contention of the department that because it was wire of larger corss-section emerging at the intermediate stages under the provisions of Rules 9 and 49 the wire becomes dutiable. The Id. Counsel submitted that what has been forgotten was that in all these 9 stages it was wire and therefore, no. new wire had come into existence as it was wire of different corss-section. Since the finally manufactured wire finer than 14 SWG was exempted from payment of duty there was no question of any duty payable on such wires at intermediate stage. The Id. Counsel therefore prayed that the impugned order may be upheld and the appeal may be rejected. The Id. Counsel also submitted that the demand was time barred as there was no mis-statement of facts on their part.