(1.) AS per facts on record, the appellants imported a capital equipment on 17th September, 1993 from their foreign supplier in Switzerland under Bill of Entry No. 4356 dated 26th September, 1993. A duty of Rs. 16,71,461.00 (Rupees sixteen lakhs seventy-one thousand four hundred and sixty-one) was paid by them on the said goods. The said equipment was installed in the appellants' factory. According to them, it started giving some problems in 1996 and they got in touch with their foreign supplier, but deposed their technical person for inspection etc. It was found that grinding roll was damaged and has to be replaced by the foreign supplier under a mutually agreed warranty against manufacturing defects. On 16th January, 1997, the defective goods were despatched by their foreign supplier. AS per the appellants, though the said goods were free replacement, the foreign supplier raised the invoice against 100% payment by mistake. Subsequently, on discussions, it was clarified that the goods sent by them were free replacement and the papers were accordingly amended as the appellants cleared the said goods on payment of duty inasmuch as the invoice originally issued by the foreign supplier showed that the delivery was against 100% payment.
(2.) Inasmuch as subsequently the invoice was amended and a written confirmation was sent by their foreign supplier. As regards the goods being free replacement, the appellants filed a refund claim of duty paid by them in terms of Notification 80/Cus., dated 29th August, 1970. The said refund claim has been rejected by the authorities below of two grounds. Firstly, that the goods sent as free replacement after a period of about 4 years from the original import cannot be said to be within the warranty period and secondly, the appellants have not been able to satisfy the authorities that the duty burden has not been based on to their customer.
(3.) WE have also heard Shri T.K. Kar, ld. SDR who reiterates the reasoning of the authorities below.