LAWS(CE)-2001-4-640

M/S. NAHAR FIBRES Vs. CCE, CHANDIGARH

Decided On April 16, 2001

JUDGEMENT

(1.) ARGUING the case for waiver of pre -deposit of duty, Shri Harbans Singh, Counsel submits that in the instant case the applicants had already discharged the duty liability at the spindle stage as single yarn in accordance with two Trade Notice Nos.70/94 -CE dt.7.6.94 and 112/94 -CE dt.15.12.94.

(2.) He submits that their case is fully covered by the decision of this Tribunal in the case of Vardhman Spinning & General Mills Limited (Final Order No.720/98 -D dt.18.9.98 and CCE vs. GIS Limited (Final Order No.136 & 137/2000 -A). He submits that in a similar circumstances, this Tribunal in the case of M/s. Arihant Spinning Mills in para 5 held that "Under these circumstances, in our view, it is a fit case where waiver of pre -deposit of entire duty amount deserves to be allowed for the purpose of hearing the appeal. Accordingly, we allow the stay application of the applicants and grant waiver of the pre -deposit of the entire duty amount in dispute and stay its recovery." He, therefore prays that pre -deposit of duty may be waived.

(3.) WE have heard the rival submissions. We note that in the instant case the duty was paid at the time of spindle stage of single yarn and since the duty was paid at the spindle stage of single yarn, there was no question of payment of duty at the doubled/multifolded yarn stage till then doubling/multifolding of yarn was not declared as process of manufacture. Thus, we find that the appellants have good prima facie case in their favour. We also note that under similar circumstances this Tribunal in the Case of Arihant. Spinning Mills waived pre -deposit therefore in the instant case, we also waive pre -deposit of duty. Accordingly pre -deposit of duty is waived and recovery thereof is stayed. The matter should now come up for hearing on 9.5.2001.