(1.) THIS is an application for stay of recovery and dispensing with pre -deposit of duty and penalty.
(2.) ARGUING the stay petition, Shri V. Lakshmikumaran, ld. Advocate submits that the applicant entered into an agreement with M/s. Shree Am -bica Sugars Limited for erection of a 70 tonnes per hour capacity bagasse fired steam boiler; that the erection contract was given to sub -contractor of the applicant; that the department alleged that the boiler erected at site was goods; that the applicant was the manufacturer and since it was goods, the department demanded Rs. 76,81,542.00 as duty and imposed equal amount of statutory penalty.
(3.) LD .Counsel submits that the boiler was not 'goods', looking to the size and its erection. He submits that the boiler was embedded to the earth and, therefore was not 'goods' for the purpose of levy and collection of duty. He submits that even if the boiler is considered as goods, it was using bagasse (agricultural waste) for producing heat energy. He submits that the CBEC clarified that the boiler can be treated as conversion device. He submits that if the boiler used in the instant case is considered as conversion device using agricultural waste (bagasse) for producing heat energy it was fully covered by the exemption Notf. No. 5/98. He submits that there is an affidavit filed by the manufacturer of sugar that the boiler was using bagasse for producing heat energy. He submits that the department's contention is that the sugar manufacturers are using bagasse only for conversion of water into steam. He submits that therefore the boiler in the instant case was exempt under Notf. No. 5/98. In support of his contention, ld. Counsel cites a number of decisions on the issue specially the decision of the Tribunal on Elecon Engineering and Thermax Surface Coating Limited.