LAWS(MHCDRC)-2009-9-16

SUHAIL JABBAR SHAIKH Vs. ORIENTAL INSURANCE CO. LTD

Decided On September 17, 2009

JUDGEMENT

(1.) The complainant whose complaint was dismissed by the Forum below has filed this appeal challenging the dismissal order. In filing this appeal, there is delay of 255 days. Hence, complainant/appellant herein has filed condonation of delay application bearing No.1324/2008.

(2.) We heard Mr.R.K. Dave, Advocate for the appellant and Mr.J.S. Chandnani, Advocate for the respondent. We have also perused the application for condonation of delay.

(3.) The appellant has mentioned that he was out of town and his Advocate was not keeping well and therefore, he could not file appeal within limitation. However, in filing appeal, there is delay of 255 days and doctors certificate produced in support of condonation of delay application simply mentioned that complainants Advocate Mr.Harshad Trivedi was in his hospital for some days and he was advised to take bed rest of one month. So, even after discharge of Advocate Mr.Harshad Trivedi from the hospital, he was simply directed to take bed rest for one month. So, this certificate is not helpful to seek condonation of delay of 255 days. Misc. Application for condonation of delay is drafted in omnibus manner and no specific plea is taken to give strong and compelling reason or ground as to why complainant/appellant was unable to file appeal for so many days. We are not satisfied about just and sufficient grounds mentioned in the condonation of delay application. As such same is liable to be rejected. Hence, the following order :- Order:-