(1.) THIS is a Petition filed by M/s Shyam Telelink Ltd., New Delhi which holds a licence under Section 4 of the Indian Telegraph Act, 1885 to establish, maintain and operate Basic Telephone Service in Rajasthan Telecom Circle. The Petitioner has approached this Tribunal under Section 14(a)(i) read with Section 14A(I) of the Telecom Regulatory Authority of India Act, 1997 on the ground that the licensor, viz., Department of Telecommunications has levied and collected huge amounts from the Petitioner in an arbitrary and wrongful manner.
(2.) The fats of the case are briefly as under. The Petitioner was granted a licence under Indian Telegraph Act, 1885 on 4.3.1998 to provide basic telecom services in Rajasthan Circle. The Licence Agreement provided for (a) a fixed annual licence fee, (b) a Financial Bank Guarantee of Rs. 25 crores and (c) a Performance Bank Guarantee of Rs. 25 crores and (c) a Performance Bank Guarantee of Rs. 25 crores, apart from several other conditions. The "effective date" for the purpose of the licence was the same date as that of signing of the licence agreement, viz., 4.3.1998. As per Clause 4 (Schedule 'B' - Part I) of the licence agreement, the licensee was required to start commercial operations within 12 months from the effective date, i.e., on or before 4.3.1999. The Petitioner has alleged that even though it was ready to commence commercial operations in the last week of February 1999 and had in fact sought the permission of the Respondent to do so, such permission was denied and the Petitioner was asked to fulfill certain conditions and rectify certain technical deficiencies. According to the Petitioner, the Respondent gave permission to certain other operators, including Mahanagar Telephone Nigam Limited (MTNL) in other circles even though identical technical deficiencies as well as non-fulfilment of conditions were present in those cases. The Petitioner ultimately had to pay liquidated damages to the extent of Rs. 7.30 crores when as a part of a general rehabilitation measure the Union Government offered a Migration Package in July 1999 to all the Telecom Operators. Under the Migration Package offered to the Petitioner on 22.7.1999, the fixed licence regime was changed to a revenue-sharing arrangement with effect from 1.8.199, subject to the stipulation that at least 35% of all outstanding dues including interest payable as on 31.7.1999 and liquidated damage charges in full will have to be paid on of before 15.8.1999. A further stipulation was that the Migration Package which comprised of 11 specific clauses would have to be accepted in toto and that simultaneously all legal proceedings instituted by the licensees and their Associations against the Union of India or the Department of Telecommunications shall have to be withdrawn. The Petitioner gave the required unconditional acceptance on 28th July 1999. On 10th August 1999 the Respondent advised the Petitioner about the outstanding dues including Liquidated Damage Charges payable under the Migration Package as under:
(3.) THE Petitioner commenced commercial operations in Rajasthan from 5th June, 2000. On 8th March, 2001 the Respondent advised the Petitioner that a further amount of Rs. 70 lakhs was payable as liquidated damage charges for delay in commissioning of service. This is the major bone of contention in the current dispute before the Tribunal. In its Petition the Petitioner has claimed that the action of the respondent in refusing permission to the Petitioner to commence commercial operations from the last week of February 1999 (which was well before the expiry of the stipulated period) was arbitrary, illegal and discriminatory. As such, the consequent levy of liquidated damages was bad in law. THE Petitioner has further prayed that since the delays in commencing commercial operations were entirely due to the acts of omission and commission by the Government, the entire amount of liquidated damages amounting to Rs. 8 crores should be refunded to the Petitioner.