(1.) "Should the State Commission revise any formula or otherwise the tariff in the middle of the tariff year after having determined the revenue requirements and consequently the tariff to meet the revenue requirements and that too retrospectively which may cause financial burden/cash flow problems to the Licensee including the cost reflecting tariff will not be recovered by the licensees - This is the question posed for consideration in this Appeal.
(2.) THE Appellants are the distribution Licensees in the State of Madhya Pradesh. Madhya Pradesh Electricity Regulatory Commission (State Commission) is the 1st Respondent herein. 2nd and 3rd Respondents are the consumers of electricity.
(3.) AGGRIEVED by the Order dated 7.10.2010 passed by the State Commission the Appellants have filed this Appeal.